Add Days to a Date

Add or subtract days, weeks, months and years from a date, or count working days forward and back, skipping weekends and public holidays.

Frequently Asked Questions

Is the start date counted?

No. The start date is day 0, so adding 1 day gives the next day.

What happens when I add a month to the 31st?

If the day doesn’t exist in the month you end up in, the last day of that month is used. So 31 January plus 1 month gives 28 February, or 29 February in a leap year.

How are working days counted?

Weekly days off and the public holidays you choose are skipped. The result is the working day that lies the chosen number of working days after the start date. The start date itself is never counted, even if it is a working day.

In which order are years, months, weeks and days added?

Years and months are added first, then weeks and days. Subtracting works in the same order.